Contract Bid Abstract

20:01B - CSAH 1 ResurfacingAnderson Brothers Construction Company of Brainerd Mark Sand & Gravel Co R. J. Zavoral & Sons Inc. Central Specialties Inc. Knife River Corporation Duininck Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2104.503REMOVE CURB & GUTTERL F300$8.50$2,550.00$25.00$7,500.00$7.00$2,100.00$12.00$3,600.00$6.30$1,890.00$10.60$3,180.00
2104.503REMOVE CURB & GUTTERL F100$10.00$1,000.00$25.00$2,500.00$7.00$700.00$12.00$1,200.00$8.00$800.00$10.60$1,060.00
2104.507REMOVE AGGREGATEC Y17,015$17.50$297,762.50$14.00$238,210.00$21.25$361,568.75$30.00$510,450.00$20.00$340,300.00$19.60$333,494.00
2104.507REMOVE AGGREGATEC Y2,542$17.50$44,485.00$14.00$35,588.00$21.25$54,017.50$30.00$76,260.00$19.25$48,933.50$19.25$48,933.50
2215.504FULL DEPTH RECLAMATIONS Y16,651$0.95$15,818.45$1.55$25,809.05$1.85$30,804.35$2.00$33,302.00$1.10$18,316.10$1.35$22,478.85
2215.504FULL DEPTH RECLAMATIONS Y111,435$0.92$102,520.20$1.55$172,724.25$1.85$206,154.75$2.00$222,870.00$1.22$135,950.70$1.30$144,865.50
2232.504MILL BITUMINOUS SURFACES Y778$5.25$4,084.50$20.00$15,560.00$7.00$5,446.00$5.00$3,890.00$5.45$4,240.10$5.13$3,991.14
2360.509TYPE SP 9.5 WEARING COURSE MIX (3;C)TON15,028$54.00$811,512.00$54.25$815,269.00$53.20$799,489.60$60.24$905,286.72$57.75$867,867.00$68.75$1,033,175.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (3;C)TON33,018$51.15$1,688,870.70$51.30$1,693,823.40$51.70$1,707,030.60$46.00$1,518,828.00$56.75$1,873,771.50$64.60$2,132,962.80
2360.509TYPE SP 9.5 WEARING COURSE MIX (3;C)TON1,382$54.00$74,628.00$54.25$74,973.50$53.20$73,522.40$60.24$83,251.68$57.50$79,465.00$68.75$95,012.50
2360.509TYPE SP 12.5 WEARING COURSE MIX (3;C)TON3,223$51.15$164,856.45$51.30$165,339.90$51.70$166,629.10$46.00$148,258.00$56.50$182,099.50$64.60$208,205.80
2531.503CONCRETE CURB & GUTTER DESIGN B618L F300$33.75$10,125.00$100.00$30,000.00$54.25$16,275.00$66.00$19,800.00$32.00$9,600.00$45.00$13,500.00
2531.503CONCRETE CURB & GUTTER DESIGN B618L F100$33.75$3,375.00$100.00$10,000.00$54.25$5,425.00$82.00$8,200.00$32.00$3,200.00$45.00$4,500.00
2540.602MAIL BOX SUPPORTEACH12$110.00$1,320.00$125.00$1,500.00$115.00$1,380.00$120.00$1,440.00$105.00$1,260.00$120.00$1,440.00
2540.602MAIL BOX SUPPORTEACH3$110.00$330.00$125.00$375.00$115.00$345.00$120.00$360.00$105.00$315.00$120.00$360.00
2563.601TRAFFIC CONTROLLS0.09$3,800.00$342.00$5,000.00$450.00$7,000.00$630.00$1,935.00$174.15$25,000.00$2,250.00$2,100.00$189.00
2563.601TRAFFIC CONTROLLS0.91$3,600.00$3,276.00$5,000.00$4,550.00$7,000.00$6,370.00$1,935.00$1,760.85$17,000.00$15,470.00$2,100.00$1,911.00
2574.507COMMON TOPSOIL BORROWC Y1,074$26.50$28,461.00$33.50$35,979.00$40.00$42,960.00$68.00$73,032.00$40.00$42,960.00$30.00$32,220.00
2574.507COMMON TOPSOIL BORROWC Y161$26.50$4,266.50$33.50$5,393.50$40.00$6,440.00$68.00$10,948.00$47.00$7,567.00$30.00$4,830.00
2575.523RAPID STABILIZATION METHOD 3MGAL2.1$525.00$1,102.50$545.00$1,144.50$590.00$1,239.00$545.00$1,144.50$545.00$1,144.50$545.00$1,144.50
2575.523RAPID STABILIZATION METHOD 3MGAL14.1$525.00$7,402.50$545.00$7,684.50$590.00$8,319.00$545.00$7,684.50$545.00$7,684.50$545.00$7,684.50
2580.503INTERIM PAVEMENT MARKINGL F1,478$1.60$2,364.80$1.00$1,478.00$1.35$1,995.30$1.00$1,478.00$0.10$147.80$0.50$739.00
2580.503INTERIM PAVEMENT MARKINGL F220$1.60$352.00$1.00$220.00$1.35$297.00$1.00$220.00$0.10$22.00$0.50$110.00
2582.5034" SOLID LINE MULTI COMPL F3,839$0.25$959.75$0.22$844.58$0.22$844.58$0.20$767.80$0.23$882.97$0.23$882.97
2582.5034" BROKEN LINE MULTI COMPL F756$0.25$189.00$0.22$166.32$0.22$166.32$0.20$151.20$0.23$173.88$0.23$173.88
2582.5036" SOLID LINE MULTI COMPL F7,556$0.36$2,720.16$0.31$2,342.36$0.31$2,342.36$0.29$2,191.24$0.29$2,191.24$0.29$2,191.24
2582.5034" SOLID LINE MULTI COMPL F25,690$0.25$6,422.50$0.22$5,651.80$0.22$5,651.80$0.20$5,138.00$0.23$5,908.70$0.23$5,908.70
2582.5034" BROKEN LINE MULTI COMPL F5,056$0.25$1,264.00$0.22$1,112.32$0.22$1,112.32$0.20$1,011.20$0.23$1,162.88$0.23$1,162.88
2582.5036" SOLID LINE MULTI COMPL F50,556$0.36$18,200.16$0.31$15,672.36$0.31$15,672.36$0.29$14,661.24$0.35$17,694.60$0.29$14,661.24
2582.50324" SOLID LINE PREF TAPE GR IN (WR)L F24$44.50$1,068.00$44.00$1,056.00$47.00$1,128.00$44.00$1,056.00$70.00$1,680.00$70.00$1,680.00
2582.518PAVT MSSG PREF TAPE GR IN (WR)S F49.86$52.75$2,630.12$48.60$2,423.20$52.65$2,625.13$48.60$2,423.20$53.00$2,642.58$53.00$2,642.58
 Totals for project 20:01B $3,304,258.79 $3,375,340.54 $3,528,681.22 $3,660,838.28 $3,677,591.05 $4,125,290.58
 
20:13B - CSAH 13Anderson Brothers Construction Company of Brainerd Mark Sand & Gravel Co R. J. Zavoral & Sons Inc. Central Specialties Inc. Knife River Corporation Duininck Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2104.502SALVAGE PIPE APRONEACH4$525.00$2,100.00$1,000.00$4,000.00$325.00$1,300.00$1,000.00$4,000.00$400.00$1,600.00$816.00$3,264.00
2104.507REMOVE AGGREGATEC Y9,456$20.00$189,120.00$14.85$140,421.60$30.50$288,408.00$25.00$236,400.00$15.00$141,840.00$18.85$178,245.60
2118.509AGGREGATE SURFACING CLASS 1TON168$25.00$4,200.00$30.00$5,040.00$19.65$3,301.20$30.00$5,040.00$42.00$7,056.00$41.00$6,888.00
2215.504FULL DEPTH RECLAMATIONS Y87,811$0.93$81,664.23$1.55$136,107.05$1.85$162,450.35$1.60$140,497.60$1.22$107,129.42$1.30$114,154.30
2360.509TYPE SP 9.5 WEARING COURSE MIX (3;C)TON10,404$52.00$541,008.00$54.25$564,417.00$53.20$553,492.80$52.43$545,481.72$61.00$634,644.00$64.10$666,896.40
2360.509TYPE SP 12.5 WEARING COURSE MIX (3;C)TON10,097$49.00$494,753.00$51.30$517,976.10$53.20$537,160.40$52.43$529,385.71$60.00$605,820.00$59.00$595,723.00
2540.602MAIL BOX SUPPORTEACH11$110.00$1,210.00$125.00$1,375.00$115.00$1,265.00$120.00$1,320.00$105.00$1,155.00$120.00$1,320.00
2540.602RELOCATE MAIL BOXEACH8$95.00$760.00$75.00$600.00$97.00$776.00$75.00$600.00$90.00$720.00$75.00$600.00
2563.601TRAFFIC CONTROLLS1$5,100.00$5,100.00$6,000.00$6,000.00$8,350.00$8,350.00$2,800.00$2,800.00$6,700.00$6,700.00$3,570.00$3,570.00
2574.609COMMON TOPSOIL BORROWTON2,730$22.00$60,060.00$22.40$61,152.00$28.75$78,487.50$36.00$98,280.00$30.00$81,900.00$30.00$81,900.00
2575.523RAPID STABILIZATION METHOD 3MGAL17$525.00$8,925.00$545.00$9,265.00$590.00$10,030.00$545.00$9,265.00$545.00$9,265.00$545.00$9,265.00
2580.503INTERIM PAVEMENT MARKINGL F4,272$1.60$6,835.20$1.00$4,272.00$1.35$5,767.20$1.00$4,272.00$0.81$3,460.32$0.50$2,136.00
2582.5034" SOLID LINE MULTI COMPL F10,851$0.25$2,712.75$0.22$2,387.22$0.22$2,387.22$0.20$2,170.20$0.23$2,495.73$0.23$2,495.73
2582.5034" BROKEN LINE MULTI COMPL F5,354$0.25$1,338.50$0.22$1,177.88$0.22$1,177.88$0.20$1,070.80$0.23$1,231.42$0.23$1,231.42
2582.5036" SOLID LINE MULTI COMPL F53,540$0.36$19,274.40$0.31$16,597.40$0.31$16,597.40$0.29$15,526.60$0.29$15,526.60$0.29$15,526.60
2582.50324" SOLID LINE PREF TAPE GR IN (WR)L F36$44.00$1,584.00$44.00$1,584.00$47.00$1,692.00$44.00$1,584.00$70.00$2,520.00$70.00$2,520.00
2582.518PAVT MSSG PREF TAPE GR IN (WR)S F49$52.75$2,584.75$48.60$2,381.40$52.65$2,579.85$48.60$2,381.40$53.00$2,597.00$53.00$2,597.00
 Totals for project 20:13B $1,423,229.83 $1,474,753.65 $1,675,222.80 $1,600,075.03 $1,625,660.49 $1,688,333.05
 
4005 - Phelps Mill OverlayAnderson Brothers Construction Company of Brainerd Mark Sand & Gravel Co R. J. Zavoral & Sons Inc. Central Specialties Inc. Knife River Corporation Duininck Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
 Totals for project 4005 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
 
Contract Total:$4,727,488.62$4,850,094.19$5,203,904.02$5,260,913.31$5,303,251.54$5,813,623.63